Reposting, allocation or correction? Choosing the right way

When to correct an amount in the original, when to repost it and when an allocation rule does the work – with seven typical practical cases and the direct and step-down allocation methods.

If an amount is in the wrong place in cost accounting, there are three ways to deal with it: correct the primary element, repost it or set up an allocation. Which one is right depends on whether it is an error, a one-off or something recurring. This article helps you decide; how to operate the functions is described in Repost an amount and Set up an allocation rule.

Three situations, three ways

SituationWayExample
Genuine errorcorrect it in the primary element (time booking, cost element, line item, posting)expenses posted to the wrong project
One-offreposting: one amount, manually, with a descriptiona trip was for two customers; part of a trade fair belongs to a different cost category
Recurringallocation: a rule distributes automatically every periodIT costs to the areas every month

Rule of thumb: if the same reposting comes back every month, it is no longer a reposting but an allocation.

Why not simply change the original? Because a one-off such as a trip for two customers is one transaction with one expense claim. Splitting it artificially when recording distorts the expense report and the financial accounting view. A reposting leaves the original unchanged and is a separate record with a description and a user.

Seven typical cases

Each case has exactly one way, and each way respects the principle “Σ cost centres = Σ cost objects” (see Two views, one result).

No.ProblemSolutionRouteGuide
1A trip for two customers is recorded on one projectmanual repostingcost object → cost objectRepost an amount
2The department doing the work is to receive a share of the marginmanual reposting, cost category internal charge mark-upcost centre → cost centreRepost an amount
3IT, administration and management belong to the areasservice cost centre with allocation rulecost centre → cost centreSet up an allocation rule
4Servers and pools belong to the projectsreal cost centre + intermediate cost object with allocation rulecost object → cost objectSet up an allocation rule
5The salary is missing, personnel costs are only estimatedsalary cost centre: time bookings relieve it, the remainder is allocatedsalary cost centre → cost objectSalary cost centre
6Someone works for another areaowner cost centre on the cost objectno postingTypes and structure
7A cross-posting from the cost centre to the cost object counts twiceleave the “Cross-posting” switch offblockedTwo views, one result

Why case 2 is not a reposting to the project

A developer works 40 hours on a consulting customer project. The project belongs to consulting, so that is where the whole margin ends up. The obvious mistake would be a reposting from development to the project. The posting would then switch views: the cost object total would be too high by that amount, the cost centre total too low.

The margin is a matter between two areas, not a matter for the project. That is why it is reposted from cost centre to cost centre, and the project CM stays unchanged. You decide how large the share is: a fixed mark-up per hour (simple and predictable) or a share of the project CM by hours (fairer, but only properly calculable at the end of the project).

Allocation methods: direct and step-down

The methods differ in whether service cost centres also exchange services with each other.

MethodHow it worksIn teamspace
Direct methodEach service cost centre distributes directly to the final cost centres. Services between service cost centres are ignored. Good for small tenants and clear structures.✓ all rules at the same time
Step-down methodThe service cost centres are distributed one after the other, e.g. first management, then administration and IT. Once distributed, a cost centre receives nothing back. The standard in practice.✓ via staggered rule schedules
Reciprocal methodMutual services (IT works for administration and vice versa) are solved simultaneously using a system of equations.not supported

This is what a step-down looks like:

ScheduleRuleDistributes
3rd of the month, 10:00management rulemanagement → administration, IT
3rd of the month, 11:00administration and IT rules→ consulting, development, support

Each rule empties its source completely. After 11:00, all service cost centres are at zero. There are deliberately no fixed percentages: amounts are distributed evenly or by allocation weights.

How to recognise secondary postings

  • By the cost category: repostings and allocations use their own cost categories in class 9000, e.g. 9200 Reposting, 9310 Allocation administration, 9320 Allocation IT. Create a separate cost category for each allocation, then you can see straight away in the movements where an amount comes from.
  • In the movements: in the detail manager, secondary postings are listed with direction, type and counterpart.
  • On the record: manual repostings and automatic allocations are both separate records. The original remains unchanged.